EPD waste transfer station upgrade wins BIM excellence award
Bastillepost · 1 SOURCESabout 2 hours ago2 MIN

Summary
The Environmental Protection Department said its “Island West and Island East Waste Transfer Stations Upgrade and Improvement Works Project” received the Excellence BIM Award at the Autodesk Hong Kong BIM Awards 2026. According to the department, the project team applied building information modelling, or BIM, throughout both the design and construction stages to simulate engineering details in advance and refine construction arrangements. The works covered challenges at both transfer stations, including cavern-based facilities, tight working space and the need to reduce disruption to daily operations. The department said it would continue using innovative technologies such as BIM to improve project quality, efficiency and safety, while promoting digitalisation in the industry
Key Points
- At the Island West Waste Transfer Station, most facilities for a new sewage treatment system are located inside a cavern with irregular rock walls and narrow space constraints
- The team used 3D laser scanning to build an accurate three-dimensional model before simulating equipment, pipework and maintenance access through BIM
- The BIM process helped identify and resolve spatial clashes early, reducing the impact of construction works on the station’s normal daily operations
- For the Island East Waste Transfer Station, the team used 4D construction simulation linking 3D models with schedules to rehearse sequencing and equipment installation
- The project also used 3D models to simulate vessel berthing and container loading and unloading, checking compatibility with pier facilities and spotting potential issues early
Why It Matters
For Hong Kong readers, the award points to how digital engineering tools are being used in complex public works where space is limited and facilities must keep operating during upgrades. It also shows how government departments are framing BIM not only as a design tool, but as a way to improve safety, efficiency and coordination in construction delivery