Multiple elevators in Queen Mary Hospital's newly rebuilt medical building have been sealed off following a rare incident involving a registered engineer convicted of submitting false or misleading inspection documents. The hospital's new building, which began phased operations at the end of last year, has seen several elevators remain out of service, though the Hospital Authority Deputy Chief Executive has stated there is currently no impact on overall hospital services. The HK$9.45 billion construction contract was awarded in 2018 to Paul Y-Anbao Joint Venture, whose associated companies have been involved in multiple public works controversies, raising serious concerns about the integrity of Hong Kong's construction industry.

Key Points

  • A registered engineer has been convicted and is awaiting sentencing for submitting false or misleading inspection documents related to the elevator issues
  • The HK$9.45 billion contract for Queen Mary Hospital's reconstruction was awarded to Paul Y-Anbao Joint Venture in 2018
  • Baoyao Construction, one of the joint venture partners, was court-ordered to wind up last year due to unpaid engineering fees
  • Anbao Engineering, the other partner, received a one-year suspension from government tendering in January due to a screw-cutting incident at a simple public housing project
  • Anbao Engineering has nevertheless secured five public housing contracts worth HK$19.3 billion since 2024, despite the suspension

Why It Matters

The pattern of the same contractor repeatedly winning government projects despite recurring problems exposes fundamental weaknesses in Hong Kong's public works oversight system . This incident adds to a series of construction integrity crises, from the Shatin-Central Link cut reinforcing steel scandal to fatal construction site accidents, suggesting that without systemic reforms, public safety will continue to be compromised .
The pattern of the same contractor repeatedly winning government projects despite recurring problems exposes fundamental weaknesses in Hong Kong's public works oversight system . This incident adds to a series of construction integrity crises, from the Shatin-Central Link cut reinforcing steel scandal to fatal construction site accidents, suggesting that without systemic reforms, public safety will continue to be compromised .