Audit flags delays, overruns in river revitalisation works

about 8 hours ago2 MIN
Audit flags delays, overruns in river revitalisation works

Summary

A new Audit Commission report says the Drainage Services Department has room for improvement in its work to revitalise and improve rivers and nullahs, after both the Kai Tak River and Tsui Ping River projects were completed later than originally scheduled. For Kai Tak River, three works contracts were delayed by 5.1 to 31.1 months because some site boundaries overlapped and work areas could not be handed over on time. For Tsui Ping River in Kwun Tong, groundwater inflow during riverbed reconstruction and settlement during piling pushed completion back by about 10 months and led to extra compensation payments. The audit also highlighted the removal of three ecological floating beds about 1.4 years after installation, despite HK$2.7 million being spent on installing and optimising them.

Key Points

  • The Drainage Services Department awarded three Kai Tak River works contracts to three contractors, but overlapping site boundaries delayed handover of work areas.
  • Those three Kai Tak River contracts were completed 5.1 to 31.1 months late, with final contract sums totalling more than HK$1.6 billion.
  • Audit findings said decorative finishes on Kai Tak nullah walls were revised to match an existing stone wall considered to have historical value.
  • In the Tsui Ping River target contract, works were substantially completed on September 30, 2024, about 10 months behind schedule.
  • The Tsui Ping River contract recorded actual expenditure of HK$1.118 billion against a final target price of HK$931.2 million, creating an overrun of HK$186.8 million.

Why It Matters

The audit recommendations focus on practical issues that affect public works costs and delivery, including timely site handovers between related contracts, clearer verification of underground conditions and closer progress monitoring. For Hong Kong residents, the findings also raise questions about how pilot ecological features and higher-risk construction elements are tested before public money is committed.