Tung Chung Line Services to End Early on Nov 28 for Extension Works
Bastillepost · 4 SOURCESabout 4 hours ago2 MIN

Summary
MTR Corporation announced on Tuesday that train services on the Tung Chung Line between Tung Chung and Sunny Bay stations will terminate early at approximately 11 PM on Saturday, November 28. The service adjustment is necessary to accommodate critical track installation works for the Tung Chung Line Extension project, specifically the third phase of switch installation to connect with the future Tung Chung East station. Free shuttle bus services will be provided between the affected stations until normal closing time, while services between Sunny Bay and Hong Kong stations will continue as usual.
Key Points
- Train services between Tung Chung and Sunny Bay stations will end at approximately 11 PM on November 28, approximately two hours earlier than normal schedule
- Free shuttle buses will operate between Tung Chung and Sunny Bay stations until normal closing time to maintain passenger connectivity
- Services between Sunny Bay and Hong Kong stations will remain unaffected throughout the works period
- The works involve installing railway switches, or points, to allow trains to divert to the future Tung Chung East station
- The November 28 installation represents the third of four key switch installation phases, with the fourth phase expected next year
Why It Matters
The Tung Chung Line Extension is a major infrastructure project that will create a new station at Tung Chung East, expanding public transport capacity for one of Hong Kong's growing new towns. Completion of these critical track works marks another step toward the project's full realization, which will improve connectivity for residents in the northeastern Tung Chung area once operational.
The Tung Chung Line Extension is a major infrastructure project that will create a new station at Tung Chung East, expanding public transport capacity for one of Hong Kong's growing new towns. Completion of these critical track works marks another step toward the project's full realization, which will improve connectivity for residents in the northeastern Tung Chung area once operational.